*[20D. Grant of permission by competent authority within regulated area.- (1) Every application for grant of permission under section 20C of this Act shall be made to the competent authority in such manner as may be prescribed.

(2) The competent authority shall, within fifteen days of the receipt of the application, forward the same to the Authority to consider and intimate impact of such construction (including the impact of large-scale development project, public project and project essential to the public) having regard to the heritage bye-laws relating to the concerned protected monument or protected area, as the case may be:

Provided that the Central Government may prescribe the category of applications in respect of which the permission may be granted under this sub- section and the application which shall be referred to the Authority for its recommendations.

(3) The Authority shall, within two months from the date of receipt of application under sub-section (2), intimate to the competent authority impact of such construction (including the impact of large-scale development project, public project and project essential to the public).

(4) The competent authority shall, within one month of the receipt of intimation from the Authority under sub-section (3), either grant permission or refuse the same as so recommended by the Authority.


(5) The recommendations of the Authority shall be final.


(6) In case the competent authority refuses to grant permission under this section, it shall, by order in writing, after giving an opportunity to the concerned person, intimate such refusal within three months from the date of receipt of the application to the applicant, the Central Government and the Authority.


(7) If the competent authority, after grant of the permission under sub-section (4) and during the carrying out of the repair or renovation work or re-construction of building or construction referred to in that sub-section, is of the opinion (on the basis of material in his possession or otherwise) that such repair or renovation work or re-construction of building or construction is likely to have an adverse impact on the preservation, safety, security or access to the monument considerably, it may refer the same to the Authority for its recommendations and if so recommended, withdraw the permission granted under sub-section (4) if so required:


Provided that the competent authority may, in exceptional cases, with the approval of the Authority grant permission to the applicant referred to in sub-section (2) of section 20C until the heritage bye-laws have been prepared under sub-section (1) of section 20E and published under sub-section (7) of that section.


(8) The Central Government, or the Director-General, as the case may be, shall exhibit, on their website, all the permissions granted or refused under this Act.]

[*Inserted vide Ancient Monuments and Archaeological Sites and Remains (Amendment and Validation) Act, 2010]

 

 

 

 

 

A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z

 

 

Quick Links     
      
Family LawsInsurance LawsEnvironmental lawTax LawFDI 
Company LawTelecommunication LawLabour LawsCentral RulesRBI 
Business & Commercial LawsConsumer lawsCorporate lawsCriminal lawsSEBI 
Intellectual Property lawMedia & Press lawsPharma & Medical lawsProperty lawFEMA 
Debt Recovery LawsAmendmentsProfessional lawBanking LawsLegal Links 
      
      
 
 
 
 
 

 
   
 

 

 

Privacy PolicyDisclaimer

Copyright @2010