11. Priority dates
of claims of a complete specification.- (1) There
shall be a priority date for each claim of a complete specification.
(2) Where a complete specification is filed in pursuance
of a single application accompanied by-
(a) a provisional specification; or
(b) a specification which is treated by virtue of a direction
under sub-section (3) of section 9 as a provisional specification,
and the claim is fairly based on the matter disclosed in the
specification referred to in clause (a) or clause (b), the
priority date of that claim shall be the date of the filing
of the relevant specification.
(3) Where the complete specification is filed or proceeded
with in pursuance of two or more applications accompanied
by such specifications as are mentioned in sub-section (2)
and the claim is fairly based oil the matter disclosed-
(a) in one of those specifications, the priority date of
that claim shall be the date of the filing of the application
accompanied by that specification ;
(b) partly in one and partly in another, the priority date
of that claim shall be the date of the filing of the application
accompanied by the specification of the later date.
*[(3A) Where a complete specification based on a previously
filed application in India has been filed within twelve months
from the date of that application and the claim is fairly
based on the matter disclosed in the previously filed application,
the priority date of that claim shall be the date of the previously
filed application in which the matter was first disclosed.]
(4) Where the complete specification has been filed in pursuance
of a further application made by virtue of sub-section (1)
of section 16 and the claim is fairly based on the matter
disclosed in any of the earlier specifications, provisional
or complete, as the case may be, the priority date of that
claim shall be the date of the filing of that specification
in which the matter was first disclosed.
(5) Where, under the foregoing provisions of this section,
any claim of a complete specification would, but for the provisions
of this sub-section, have two or more priority dates, the
priority date of that claim shall be the earlier or earliest
of those dates.
(6) In any case to which sub-sections (2), (3), *[(3A)],
(4) and (5) do not apply, the priority date of a claim shall,
subject to the provisions of section 137, be the date of filing
of the complete specification.
(7) The reference to the date of the filing of the application
or of the complete specification in this section shall, in
cases where there has been a post-dating under section 9 or
section 17 or, as the case may be, ante-dating under section
16, be a reference to the date as so post-dated or ante-dated.
(8) A claim in a complete specification of a patent shall
not be invalid by reason only of-
(a) the publication or use of the invention so far as claimed
in that claim on or after the priority date of such claim;
or
(b) the grant of another patent which claims the invention,
so far as claimed in the first mentioned claim, in a claim
of the same or a later priority date.
*[Inserted by Patents (Amendment) Act, 2005, section 9]
|